CASE STUDY

CONFECTIONARY FACTORY

We were delighted to once again work alongside Caddick Construction, this time on a new, purpose-built warehouse in Castleford for a leading confectionary brand.

CLIENT: CADDICK CONSTRUCTION

VALUE:

£2M

LOCATION:

CASTLEFORD

CONTRACT PERIOD:

10 MONTHS

logo
CASE
STUDY

CONFECTIONARY FACTORY

CONFECTIONARY FACTORY

BACKGROUND

A leading confectionary brand  invested in the development of a new, purpose-built warehouse at its Castleford site, which first started producing the company’s famous sweets in 2015. Around 80% of its sweets bought in the UK are produced at factories in Castleford and Pontefract. The 32-acre extension of its facilities will allow the company to manage increased volumes of finished product, stock more raw materials and packaging, and will help safeguard 600 jobs across both of its West Yorkshire sites.

Caddick Construction was appointed as the main contractor and Howard Civil Engineering was appointed as the civil engineering contractor for the project. Howard’s  £2m contract covered extensive enabling works, main works, and external works over a ten-month programme. Working in close collaboration with Caddick Construction and other stakeholders, the project demanded technical expertise, flexible planning, and the use of specialist equipment to overcome various logistical and environmental challenges.

gray-bg

SCOPE OF WORK

ENABLING WORKS

Foul water connection, diversion of ducting for excavation of an attenuation tank, installation of a Puraceptor tank, foundation works and general civil support for cabin setup, excavation works for off-site water connection.

MAIN WORKS

Pile caps and main foundations, conveyor link, 278 entrance and foundations for dock levellers, complex RC works to the Flam and Chiller Store, drainage, foundations and installation of a weighbridge, link access roads, FRC works to a substation, external plant slabs, and ducting infrastructure.

EXTERNAL WORKS

The final phase of external civil packages including formation and paving of perimeter footpaths, sub-base preparation to external yards and installation of southern, eastern, and western footpaths.

PLANNING AND PHASING

Through the use of specialist techniques and equipment, and a proactive, collaborative approach, Howard Civil Engineering ensured key timeframes were met and the project remained on track for its planned completion.