Penny Pot Lane

Welcome to the Penny Pot Lane 2020 roadworks newsletter

13 January 2020

Welcome to the Penny Pot Lane roadworks newsletter for 2020.

Here you can find out information about the roadworks that are planned on Penny Pot Lane for the Persimmon Homes residential development that may affect your journeys over the next few months.

You will be aware of the King Edwin Park residential development which is currently underway off Penny Pot Lane between the Jubilee Roundabout and the Ethelburga’s Estate.

In February we will be re-commencing works to complete the new entrance into the development.

We will also be providing a drainage connection from the site which will be installed down Penny Pot Lane in an easterly direction, past the Ethelburga’s Estate.
 
Howard Civil Engineering Ltd is carrying out this work on behalf of  Persimmon Homes.
 
In order to carry out the works safely, the works will be carried out under temporary traffic signals and will include some periods of road closures.
 
These works are planned to be carried out at the same time in order to limit the period of disruption to yourselves to a minimum.
 
Traffic management for the drainage connection
Monday 3rd February – 21st February (3 weeks)
Penny Pot Lane road closure of the sharp corner (only) of Penny Pot Lane by the rear of Oakdale Golf Course in order to install the outfall connection. 
 
Friday 21st February – 21st May (13 weeks)
Installation of a pipe in Penny Pot Lane up to the Persimmon site (approx. 500m) under temporary traffic signals
 
Monday 21st May for 3 weeks (exact dates and further details to be confirmed early May, depending on progress)
Penny Pot Lane road closure near the site entrance.
 
Traffic management for the completion of the site entrance
Monday 3rd February for 8 weeks
4 way Temporary traffic signals (including Jubilee Roundabout) changing to 2 way traffic signals as soon as possible.
 
 
Unfortunately, this is likely to cause some disruption for those living off or adjacent or using Penny Pot Lane, although you will always be able to access your properties. 
 
We, Howard Civil Engineering, will keep interested parties informed of the various roadworks phases, throughout the project. 
 
We would like to encourage you to sign up to Howard Civil Engineering’s electronic newsletter by filling in the form below. The newsletters will be published every fortnight and will provide you with information about any changes to the traffic management and provide you with contact details should you wish to contact the site manager. 
 
Individual concerns regarding the road works can be forwarded to Howard Civil Engineering’s Community Liaison Officer, Lucie Jones, using the email address Penny.pot@howardcivileng.co.uk

We hope that by keeping you informed we can reduce any concerns you may have about the works over the next coming months.

Warm regards
 
Lucie Jones
Community Liaison Officer for Howard Civil Engineering Ltd
 

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list