Penny Pot Lane

Penny Pot Lane Newsletter 6

28 April 2020

Newsletter 6  First published Tuesday 28th April.
 

It has been agreed with North Yorkshire City Council that works are to recommence on site Week commencing Monday 4th May 2020. All works will be undertaken in line with the latest Site Operating Procedure outlined by the government. 

Traffic management planned for the next 2 weeks

Temporary traffic signals at the Persimmon entrance on Penny Pot Lane will be re-established on Monday 4th May for a period of 4 -5 weeks. These will be automatically operated with constant monitoring. 

Temporary traffic signals will also be reinstalled on Penny Pot Lane from Ethelburg Est to Youngman Drive for the surface water pipe connection which is progressing up Penny Pot Lane. These lights will remain in operation for approximately 3 months.

Please rest assured pedestrian and cycle access through this area will remain open at all times. 

Things are starting to take shape at the site entrance.


 

Surface water connection works on Penny Pot Lane. 

If you have queries regarding these works please email yrks.construction@persimmonhomes.com

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list