Hard Ings Road Improvement Scheme

Hard Ings Interim Newsletter

13 December 2019

 

Interim Newsletter   

(Published Friday 13th Dec)

Temporary Traffic Signals on Hard Ings Road planned this Sunday 15th December

Temporary traffic signals will be in operation on Hard Ings Road on Sunday 15th December. This is to enable us to install another duct crossing which is required for the electricity diversion works near the Leisure Centre. All access to businesses and services will remain open as usual.

We apologise for the additional traffic disruption that this will cause on Sunday. Please allow additional time for your journeys. 

A629 Traffic management changes 

During the weekend (at night) we will be altering the A629 temporary traffic management to enable us to commence works in the verge.
Please be mindful of the changes to traffic lane alignment. 

Your site contacts 

There are several ways you can contact the site team for enquiries, concerns or comments.
The following staff members are based on site full time
Bradford Council Project Manager - David Aspinall Email hardingsroad@bradford.gov.uk
Howard Civil Engineering Project Manager - Tony Kilbane 07394 567341
Visiting the site is
Howard Civil Engineering Liaison Officer/Newsletter editor - Lucie Jones 0113 249 8569

Or contact me, Lucie Jones on Hard.Ings@howardcivileng.co.uk

 

 

 

 

 

 

 

 

 

 

 

Comment or Join our mailing list

To receive our regular newsletter, keeping you up to date with the progress of the works as well as advance warning of activities that may affect traffic, you can join our mailing list. Please fill in your details below and tick the 'Add me to your mailing list' box.

Add me to your mailing list