Gateway 36 Newsletter No 14 Week commencing Monday 12th July. First published Friday 9th July. 

Welcome to the Gateway 36 e-newsletter. Each fortnight, these e-newsletters will provide you with updates on progress, traffic management and any potential disruption surrounding the Gateway 36 development in Rockingham. Please note these works will be ongoing until late Summer 2021.

Progress, the past two weeks

We have continued to form the new S278 roundabout along the western side of Dearne Valley Parkway which will facilitate entry to Phase 3 of the Gateway 36 scheme. Traffic management measures to close lanes remain in place in this area.

We have now laid all the kerbs for this phase of works, in addition to diverting an existing high voltage main and preparing for upcoming tarmac surfacing in this area.

Major earthworks have continued on the main development, including the construction of a large, reinforced earth embankment around the highest development plateau.

We have also commenced additional earthworks to the development plateaus on phase 3 (north of Dearne Valley Parkway) which will also be complete later this summer.

The next two weeks

Over the next two weeks, work to form the new S278 roundabout will continue on both sides of Dearne Valley Parkway as we prepare for the completion of service diversions and tarmac surfacing in the coming weeks. This will be followed by the installation of street lighting columns, road signage, and temporary white lining.

Once the works described above are complete, traffic will then switch over to the new formed route whilst we continue work on the central section to form the new roundabout on Dearne Valley Parkway.

Earthworks on both phases of the development will continue as we progress works on the reinforced embankment and on-site processing.

The current traffic management layout will be in place whilst work to construct the new roundabout is ongoing.

Should you experience or witness an out-of-hours emergency regarding the traffic management measures in place, please call RTS on 01724 848 246.

All works are scheduled to be complete for late summer 2021. 

We are pleased to say that throughout the month of June, Howard Civil engineering offset 189.64mt CO2e on this site - achieving CCB Gold! This mitigates the use of 74,486 litres of Gasoil for the same period. This has been compensated for by investing in both the Katingan Peatland Reforestation and Conservation Project and the 86 MW Hydro Project in Himachal Pradesh.

How the new access road will look upon completion

How the new S278 roundabout will look upon completion

Your site contacts

There are several ways you can contact the site team to report faults, voice any concerns or ask any questions you may have. 

The Gateway 36 scheme is managed by the following members of our experienced and highly approachable team: Tony Kilbane (Contracts Manager), Thomas Barrett (Site Manager), Steve Thackray (Site Supervisor) and George Bagnall (Site Engineer). Please rest assured there will always be a representative on site during working hours should you have you questions about the scheme.

To contact Howard Civil Engineering remotely, please contact your Community Liaison Officer, Sophie Henderson, at rockingham@howardcivileng.co.uk or contact 07793654086.

Comment or Join our mailing list